Reynolds Construction Company (N) Limited v The Attorney General & 2 Others (Miscellaneous Cause 127 of 2023)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the application for interim measures of protection was dismissed. The court found that there was no arbitration agreement between the applicant and the third respondent (the bank) regarding the performance guarantee dispute. The disputes subject to arbitration between the applicant and the second respondent concerned only prolongation claims and liability for remedial works, not the legality of cancelling or cashing the guarantee. Furthermore, the performance guarantee had been cancelled in breach of contract when the applicant instructed cancellation based on certificates signed by the Supervisor's Representative rather than the Supervisor as required by the contract. The applicant did not come with clean hands and the existing guarantee had already been cancelled, rendering the orders sought nugatory.
Outcome
Application for interim measures dismissed; arbitration proceedings between applicant and second respondent to continue
Facts
The applicant entered into a contract with the Ministry of Finance for reconstruction of the Mbarara-Ntungamo-Kabale-Katuna Road. A performance guarantee of EUR 6,580,855.81 was issued by the third respondent bank. The applicant claimed the works were completed and the defects liability period expired in February 2018. The bank cancelled the guarantee in 2018 on the applicant's instructions after being provided with a final acceptance certificate and final statement of account signed by the Supervisor's Representative (COWI). However, the contract required these documents to be signed by the Supervisor (UNRA), not the Supervisor's Representative. Damage to the road occurred in May 2018 after the defects liability period allegedly expired. In 2021, the second respondent demanded the bank cash the guarantee to pay for remedial works. The bank refused, stating the guarantee had been cancelled. Conciliation attempts failed and the applicant commenced arbitration in November 2023, then sought interim measures to restrain cashing of the guarantee.
Issues
- Whether this is a proper case for issuance of interim measures of protection by way of mandatory injunction restraining respondents from cashing a performance guarantee pending determination of arbitral proceedings.
- Whether the conciliation process contemplated by the contract had failed, entitling the applicant to proceed to arbitration.
- Whether there is an arbitration agreement covering the dispute regarding the performance guarantee between the applicant and the third respondent.
- Whether the applicant came to court with clean hands, having cancelled the performance guarantee based on certificates not signed by the Supervisor as required by the contract.
Orders
- Application dismissed with costs to the first and second respondents.
Rules and key headnotes
Legislation cited (5)
Cases cited (2)
- John Sekaziga and another v Church Commissioners Holding Company Ltd (Miscellaneous Cause 15 of 2013)
- Byaruhanga & 2 others v Kabagahya (Miscellaneous Application 564 of 2016)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.