Roko Construction Limited v Pearl Jubilee Estates Limited and Another (Miscellaneous Cause 83 of 2021)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held: Application for interim injunction dismissed. While the applicant established a serious question for arbitration, it failed to establish a strong prima facie case of manifest fraud or that the guarantee was called with absolutely no basis. The respondent could honestly have believed in the validity of its demand under the performance guarantee. The balance of convenience favoured the respondent, as an injunction would provide the applicant with complete relief pending arbitration, while the guarantee serves as a contractual risk allocation tool and may expire before arbitration concludes.
Outcome
Application for interim injunction dismissed with costs to the 1st respondent
Facts
On 1 April 2019, the applicant contracted with the 1st respondent to construct 240 apartments for US$ 8,498,797, with completion scheduled for 30 September 2021. The contract was varied on 1 August 2021 to add 120 units for US$ 3,828,645.49, with a revised completion date of 18 December 2021. The applicant obtained an advance payment guarantee for US$ 569,595.04 and a performance guarantee for US$ 1,232,732.48 from the 2nd respondent. The 1st respondent made an advance payment of 10% of the original contract price. Dissatisfied with progress, the 1st respondent terminated the contract on 20 April 2021 when works were only 23% complete. By termination, the 1st respondent had paid US$ 1,824,533 to the applicant. The parties entered a Mutual Release and Settlement Agreement on 5 May 2021, agreeing to a joint audit. The final accounts showed the applicant owed the 1st respondent US$ 929,084, to be paid in 12 monthly instalments from 30 June 2021. The agreement provided that if three consecutive payments were missed, the 1st respondent could recover from the applicant's sister company in Kenya, and failing that, could call on the guarantees. When the applicant defaulted, the 1st respondent called on both guarantees. The applicant then applied for an interim injunction pending arbitration.
Issues
- Whether the applicant has a prima facie case with a probability of success to support the grant of an interim injunction restraining encashment of bank guarantees pending arbitration.
- Whether the applicant will suffer irreparable harm if the injunction is not granted.
- Whether the balance of convenience favours granting the injunction.
- Whether the terms for encashment of the guarantees were varied by the Mutual Release and Settlement Agreement.
- Whether the call on the guarantees constitutes fraud sufficient to warrant injunctive relief.
- Whether the respondent could not honestly have believed in the validity of its demand under the guarantee.
Orders
- Application dismissed.
- Costs awarded to the 1st respondent.
Rules and key headnotes
Legislation cited (3)
Cases cited (13)
- E.A. Industries v Trufoods [1972] EA 420
- American Cyanamid Co v Ethicon Limited [1975] AC 396
- Geilla v Cassman Brown Co Ltd [1973] EA 358
- GAPCO Uganda Limited v Kaweesa and Another (Miscellaneous Application No. 259 of 2013)
- G&S Engineering Services v MACH Energy Australia Pty Ltd [2019] NSWSC 407
- Leonardo SpA v Doha Bank Assurance Company LLC [2019] QIC (F) 6
- Alternative Power Solution Ltd v Central Electricity Board [2014] UKPC 3
- Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] 1 All ER 976
- Simon Carves Ltd v Ensus UK Ltd [2011] EWHC 657 (TCC)
- Doosan Babcock Ltd v Commercializadora de Equipos y Materiales Mabe Limitada [2013] EWHC 3010 (TCC)
- United Trading Corporation SA v Allied Arab Bank Ltd [1985] 2 Lloyd's Rep 554
- Barclay Mowlem Construction Ltd v Simon Engineering (Aust) Pty Ltd (1991) 23 NSWLR 451
- Yuanda (UK) Co Ltd v Multiplex Construction Europe Ltd [2020] EWHC 468 (TCC)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.