Sekaziga & Anor v Church Commissioners Holding Company Ltd (Miscellaneous Cause No. 15 of 2013)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the applicant established an arguable case concerning whether the respondent's notice of termination for convenience was issued in good faith and in accordance with fair dealing principles. An interim measure of protection was necessary to preserve the applicant's right to be heard before the arbitral tribunal on the propriety of the termination notice before the 30-day notice period expired, as the right of hearing cannot be atoned for by damages.
Outcome
Interim measure of protection granted for a limited period of 40 days to preserve applicant's right of hearing before the arbitral tribunal on the notice of termination
Facts
The applicants, a firm of architects, entered into a consultancy contract dated 10 February 2011 with the respondent for the Church House Project. The applicants had worked on the project since 1975. On 22 May 2013, the respondent issued a notice of termination of the consultancy contract for convenience under clause 6.4.3, citing current circumstances surrounding the project. The applicants sought clarification on the grounds for termination but received no response from the respondent. The applicants commenced arbitration proceedings on 18 June 2013 under clause 6.18 of the contract and applied for interim measures of protection to restrain the respondent from terminating the contract and from appointing another consultant pending arbitration. The respondent argued that termination for convenience was a contractual right exercised in good faith and that the applicants' remedy lay in damages as provided in the contract.
Issues
- Whether the court should grant an interim measure of protection restraining the respondent from terminating the consultancy contract pending arbitration.
- Whether the applicant disclosed a prima facie case or arguable case.
- Whether the applicant would suffer irreparable injury that cannot be atoned for by damages.
- Whether the balance of convenience favours granting the interim measure of protection.
Orders
- Interim measure of protection granted staying the operation of the notice of termination dated 22 May 2013 for a further period of 40 days from the date of this order.
- Temporary injunction issued restraining the respondent from appointing or entering into other consultancy contracts with any third party in respect of the services envisaged under the consultancy contract dated 10 February 2011 until the hearing and determination of the arbitration, to last for a period of 40 days from the date of this order.
- The arbitral tribunal directed to determine the dispute within the period of 40 days from the date of this order.
- Costs of the application to be costs in the arbitration cause and to be decided upon by the arbitral tribunal.
Rules and key headnotes
Legislation cited (8)
Cases cited (7)
- International Investment House LLC and Another v Amos Nzeyi and Others (Miscellaneous Cause No. 11 of 2012)
- American Cyanamid Company Ltd v Ethicon [1975] 1 All ER 504
- Kiyimba Kaggwa v Katende [1985] HCB 43
- Questar Builders Inc versus CB Flooring LLC case number 03 -C - 003688
- Performance Unlimited Incorporated versus Questar Publishers Inc, United States Appeals, sixth circuit court number 95 - 6271
- Pan African Impex Versus Barclays Bank Plc and Another
- Occidental Petroleum Corporation and the Republic of Ecuador ICCID case No. ARB 06/11
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.