Seyani Brothers & Co Ltd Cassia Ltd (HCT-00-CC-CA 128 of 2011)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the application to set aside the arbitral award failed on all grounds. The court found no evidence of bias or partiality — the arbitrator gave reasons for findings and both parties had a fair hearing. The issue of client-supplied materials arose from the dispute over delay and breach of contract, falling within the arbitrator's mandate under the arbitration clause. The arbitrator did not exceed his scope in awarding special and general damages, as these remedies were prayed for in the pleadings. The applicant failed to prove any trade usage requiring specific treatment of architects versus quantity surveyors. The court upheld the principle that applications to set aside arbitral awards are not appeals and courts will not re-evaluate evidence or substitute their judgment for the arbitrator's.
Outcome
Arbitral award upheld. Application dismissed with costs to the respondent.
Facts
Seyani Brothers and Cassia Ltd entered into a construction agreement on 18 August 2007 for Seyani Brothers to construct a resort facility at Buziga Hill in Kampala. The contract ended in dispute and Cassia Ltd filed HCCS No. 60 of 2008. By consent order dated 30 April 2010, the suit was referred to arbitration with Hon. Justice Mulenga appointed as arbitrator. On 11 February 2011, the arbitrator issued an award. The arbitrator awarded Seyani Brothers USD 109,080 for unpaid balance with interest. Cassia Ltd was awarded on its counterclaim USD 100,000 in unliquidated damages for lost income, USD 193,758 in special damages, and UGX 10,000,000 in general damages, all with interest. Costs were awarded to Cassia Ltd at two-thirds. Seyani Brothers sought to set aside the award on grounds of alleged bias, excess of mandate, and failure to apply the Act properly.
Issues
- Whether the arbitrator exhibited evident partiality and unfairness in making the arbitral award.
- Whether the arbitral award dealt with a dispute not falling within the terms of reference to arbitration.
- Whether the arbitrator exceeded the scope of his mandate.
- Whether the arbitral award was made in accordance with the terms of the contract and trade usages as required by the Arbitration and Conciliation Act.
Orders
- Application to set aside the arbitral award dismissed.
- Costs awarded to the respondent.
Rules and key headnotes
Legislation cited (7)
- Arbitration and Conciliation Act Cap 4 s.34(1)
- Arbitration and Conciliation Act Cap 4 s.34(2)(a)(iv)
- Arbitration and Conciliation Act Cap 4 s.34(2)(a)(vi)
- Arbitration and Conciliation Act Cap 4 s.34(2)(a)(vii)
- Arbitration and Conciliation Act Cap 4 s.28(5)
- Arbitration and Conciliation Rules r.7
- Arbitration and Conciliation Rules r.13
Cases cited (7)
- Simbamanyo Estates v Seyani Brothers & Co (HCMA No. 555 of 2002)
- NIC v ARCONSULTS ARCHITECTS (1984) 1 KALR at 112
- NUCC & TE V. UGANDA BOOKSHOP [1965] EA 539
- STATE OF UP V. RAM NATH INTERNATIONAL CONST PCT LTD AIR 1996
- Nathan Karema v Attorney General (HCCS No. 1019 of 2004)
- Chevron Kenya Ltd & Another v Dagare Transporters Ltd (HCMA No. 490 of 2008)
- HARILAL V. STANDARD BANK [1967] EA 512 at 516
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.