Smile Communications Uganda Limited v ATC Uganda Limited and Another (Arbitration Cause 4 of 2022)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court set aside an arbitral award on two grounds: the arbitrator exceeded the contractually agreed 90-day timeline for delivery of the award by unilaterally extending time without the parties' mutual consent, rendering the award invalid; and the arbitrator created a reasonable apprehension of bias by dedicating a book published during the arbitration to the law firm representing the respondents, despite having worked there over 20 years earlier, which would lead a fair-minded observer to conclude there was a real possibility of partiality.
Outcome
Arbitral award set aside; matter may return to fresh arbitration before a different arbitrator
Facts
Smile Communications Uganda Limited (applicant) entered into telecommunications infrastructure agreements with ATC Uganda Limited and Eaton Towers Uganda Limited (respondents) in 2012 and 2013. Disputes arose in 2018 concerning contract amendments and electricity billing practices. The parties agreed to arbitrate their disputes under The Arbitration and Conciliation Act with a 90-day timeline for completion. The arbitrator delivered an award on 28th January 2022, over 10 months after commencement, dismissing the applicant's claims and awarding the respondents unpaid amounts plus damages. The applicant applied to set aside the award, alleging procedural irregularities, partiality, and errors of law.
Issues
- Whether the dispute between the applicant and the 2nd respondent was arbitrable or should have been determined by the Electricity Disputes Tribunal.
- Whether there were errors apparent on the face of the arbitral award justifying setting aside.
- Whether the arbitral award was contrary to public policy.
- Whether the arbitral award was made in a manner contrary to the provisions of The Arbitration and Conciliation Act.
- Whether the arbitral award was delivered beyond the statutory timelines and those set out in the arbitration agreement.
- Whether the arbitrator failed in his duty to accord equal treatment to the parties at the point of delivery of the award.
- Whether the arbitral award was procured by evident partiality or reasonable apprehension of bias on the part of the arbitrator.
Orders
- The arbitral award dated 28th January 2022 is set aside.
- Costs of the application awarded to the applicant.
Rules and key headnotes
Legislation cited (40)
- Arbitration and Conciliation Act s.4
- Arbitration and Conciliation Act s.10
- Arbitration and Conciliation Act s.12(1)
- Arbitration and Conciliation Act s.13
- Arbitration and Conciliation Act s.16(2)
- Arbitration and Conciliation Act s.16(3)
- Arbitration and Conciliation Act s.31(1)
- Arbitration and Conciliation Act s.31(8)
- Arbitration and Conciliation Act s.32(1)
- Arbitration and Conciliation Act s.33(1)(a)
- Arbitration and Conciliation Act s.34
- Arbitration and Conciliation Act s.34(2)
- Arbitration and Conciliation Act s.34(2)(a)(iv)
- Arbitration and Conciliation Act s.34(2)(a)(v)
- Arbitration and Conciliation Act s.34(2)(a)(vi)
- Arbitration and Conciliation Act s.34(2)(a)(vii)
- Arbitration and Conciliation Act s.34(2)(b)(i)
- Arbitration and Conciliation Act s.34(2)(b)(ii)
- Arbitration and Conciliation Act s.34(3)
- Arbitration and Conciliation Act s.38(1)(b)
- Civil Procedure Act s.98
- Arbitration Rules r.13
- Electricity Act s.3(q)
- Electricity Act s.51(l)
- Electricity Act s.59(1)
- Electricity Act s.61(b)
- Electricity Act s.75
- Electricity Act s.75(4)
- Electricity Act s.75(6)
- Electricity Act s.93
- Electricity Act s.109
- Electricity Act s.109(2)
- Electricity (Primary Grid Code) Regulations r.2
- Electricity (Primary Grid Code) Regulations r.12.2.1
- Electricity (Primary Grid Code) Regulations r.12.2.3
- Electricity (Tariff Code) Regulations, 2003
- Electricity (Application for Permit, Licence and Tariff Review) Regulations, 2007
- Electricity Disputes Tribunal Rules of Procedure r.4
- Weights and Measures (Electrical Meters) Rules, 2015 r.3
- Uganda Communications Act s.5
Cases cited (36)
- Premium Nafta Products Ltd v Fili Shipping Co Ltd [2008] 1 Lloyd's Rep 619
- Fiona Trust & Holding Corp v Privalov [2007] UKHL 40
- Booz-Allen & Hamilton Inc v. Sbi Home Finance Ltd. and others, (2011) 5 SCC 532
- 85 A.D.3d 502
- Vimal Kishor Shah and others v. Jayesh Dinesh Shah and others (2016) 8 SCC
- Tomolugen Holdings Ltd v Silica Investors Ltd [2015] SGCA 57
- Christ For All Nationals v Apollo Insurance Co Ltd [2002] 2 EA 366
- Genossenschaft Oesterreichischer Waldbesitzer Holzwirtschaftsbertriebe Registrierte Genossenschaft mit Beschrankter Haftung [1953] 2 All ER 1039; [1953] 1 Lloyd's Rep. 495
- London Export Corporation Ltd. v. Jubilee Coffee Roasting Co. Ltd. (1958) A.W.L.R. 661
- London Export Corporation Ltd v Jubilee Coffee Roasting Co Ltd [1958] 1 WLR 271
- Ting Kang Chung John v Teo Hee Lai Building Constructions Pte Ltd [2010] SGHC 20
- Suryadev Alloys and Power Pvt. Ltd. v. Shri Govindaraja Textiles Pvt. Ltd, AIR (2010) SC 640
- Sunway Creative Stones Sdn Bhd v Syarikat Pembenaan Yeoh Tiong Lay Sdn Bhd [2020] MLJU 658
- Ken Grouting Sdn Bhd v RKT Nusantara Sdn Bhd [2020] MLJU 1901
- NBCC Limited v. JG Engineering Pvt. Limited (2010) 2, SCC 385
- Jayesh H. Pandya and another v. Subhtex India Ltd. and Others, (2020) 17 SCC 383
- M/s Lion Engineering Consultants v. State of State of Madhya Pradesh and others (2018) 16 SCC 758
- Quippo Construction Equipment Limited v. Janardan Nirman Pvt. Limited 2020 SCC OnLine SC 419
- Salar jung Museum and another v. Design Team Consultant Pvt. Ltd, 2010 (1) ALT 435
- Michael Waibel, "Investment Arbitration: Jurisdiction and Admissibility," (2014) 5 (4) Legal Studies Research Paper Series, 67-68
- AT&T Corporation v Saudi Cable Co [2000] 2 All ER (Comm) 625
- Sinocore International Co Ltd v RBRG Trading (UK) Ltd [2018] 2 Lloyd's Rep 133
- Cohen v. Ark Asset Holdings, 268 A.D.2d 285, 286 (1st Dept. 2000)
- Lake Harbor Advisors, LLC v. Settlement Servs. Arbitration and Mediation, Inc., 175 A.D.3d 479 (2d Dept. 2019)
- Monotube Pile Corp. v. Pile Foundation Constr. Corp., 269 A.D.2d 531 (2d Dept. 2000)
- Protostorm, Inc. v. Foley & Lardner LLP, 193 AD3d 486 (1st Dept 2021)
- Re Medicaments and Related Classes of Goods (No 2) [2001] 1 WLR 700
- Porter v Magill [2002] 2 AC 357
- Taylor v Lawrence [2002] 2 All ER 353
- R v Gough [1993] AC 646
- Laker Airways Inc v FLS Aerospace Limited [1999] 2 Lloyd's Rep 45
- R v Sussex Justices, ex parte McCarthy [1924] 1 KB 256
- Egerton v Earl of Brownlow (1853) 10 ER 359
- Cooke v Turner (1845) 60 ER 449
- Halliburton Company v Chubb Bermuda Insurance Ltd [2020] UKSC 48
- Halliburton Company v Chubb Bermuda Insurance Ltd [2021] AC 1083
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.