Starlite Engineers Ltd v National Housing and Construction Co. Ltd (HCT-00-CC-CS 289 of 2013)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
A contractor who fails to follow contractual procedures for extension of time works outside the agreed period when the original completion date passes. Where a contract expressly provides that VAT shall be paid by the employer to the contractor, and the contract price is stated separately from VAT, the employer must reimburse the contractor for VAT paid to URA even though the contractor is the taxable person under VAT Act s.5(a). Termination under a contractual convenience clause is lawful where supported by legitimate commercial reasons including delays, poor workmanship, and misuse of materials.
Outcome
Judgment entered in favour of the Plaintiff for reimbursement of VAT payments with interest at court rate and costs; claims for general, exemplary, and aggravated damages dismissed
Facts
National Housing and Construction Co. Ltd awarded Starlite Engineers Ltd a contract for supply of labour services to construct two blocks of flats in Bugolobi. The contract commenced 27 April 2011 with intended completion 23 July 2012 for UGX 737,618,750. The contract provided that VAT would be paid by the Defendant to the Contractor. By 23 July 2012 the works were incomplete. The Plaintiff continued working until 13 June 2013 when the Defendant suspended work and subsequently terminated the contract citing delays, declining deployment levels, poor workmanship, and misuse of materials. The Plaintiff paid VAT to URA and sought reimbursement from the Defendant, arguing the contract obliged the Defendant to pay VAT. The Defendant contended the contract price was VAT-inclusive and that extension of time had not been granted through proper contractual procedures. Certificates 23, 24, and 25 remained unpaid at the time of suit, though the Defendant paid these amounts including interest before trial.
Issues
- Whether the Defendant unlawfully terminated the contract?
- Whether the Defendant is liable for VAT as claimed by the Plaintiff?
- Whether the Plaintiff is entitled to the remedies sought?
Orders
- An order of reimbursement of all monies paid by the Plaintiff to URA in satisfaction of the relevant VAT obligations, that is, UGX 113,273,472.
- Interest on the reimbursement amount at court rate from date of judgment until payment in full.
- Costs of the suit to the Plaintiff.
- Claims for general damages, exemplary damages, and aggravated damages dismissed.
- Claim for interest at commercial rate on outstanding sums dismissed.
Rules and key headnotes
Legislation cited (1)
- VAT Act Cap 349 s.5(a)
Cases cited (7)
- Green Boat Entertainment Ltd v City Council of Kampala (HCCS 580 of 2003)
- Stroms v Hutchinson [1905] AC 515
- Addis v Gramophone Co. Ltd [1909] AC 488
- Uganda Revenue Authority v Wanume David (CACA 43 of 2010)
- Rookes v Barnard [1964] AC 1129
- Cassell & Co. Ltd v Broome [1972] 1 All ER 801
- Uganda Revenue Authority v Stephen Mabosi (SCCA 16 of 1995)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.