Tamp Engineering Consultant Ltd v Macdowell Ltd (Civil Suit No. 224 of 2010)
Observed later treatment
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
Appeal & case history
Follow this matter from the decision below through each appellate court.
See the court’s words
“es of law in the Judgment of this court in Beatrice Odongo and Noah Ochota v Tamp Engineering Consultants; Civil Appeat No 8 of 2020 are vatid and remain, any execution proceedings and orders pursuant to the judgment in High Court (Commercial Division) Civit Suit No 224 of 2010 cannot proceed, the judgment f rom which execution proceedings arose having been set aside in this”
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court held it had jurisdiction to hear the suit as the contract stipulated Uganda law would govern and was signed in Kampala. The court found the Defendant breached the contract by taking over the road construction site and works before the contractual 28-day period for work stoppage had expired, depriving the Plaintiff of performance. Special damages of UGX 372,452,331 representing the contractual balance were awarded, along with general and exemplary damages, interest, and an order for return of equipment.
Outcome
Judgment entered for the Plaintiff with awards of special, general, and exemplary damages, interest, and order for return of equipment
Facts
The Plaintiff and Defendant entered into a road construction agreement on 15 August 2008 for rehabilitation of a 100.4 km road in South Sudan for UGX 1,600,000,000. The Plaintiff received UGX 700,000,000 advance and mobilised equipment and staff to site. Work commenced on 19 December 2008, but staff broke for Christmas on 20 December 2008. Upon returning on 18 January 2009, the Plaintiff's staff found the Defendant had taken over work operations using the Plaintiff's equipment. Communication efforts failed. The Defendant formally terminated the contract on 30 May 2009 alleging abandonment. At the time of takeover, 29 days had elapsed since work ceased. The Plaintiff alleged it was prevented from accessing the site and equipment. The Defendant claimed the Plaintiff abandoned the site after receiving 75% of the contract sum but only completing less than 15% of the work.
Issues
- Whether the court had jurisdiction to determine the matter.
- Whether the Defendant breached the contract.
- What remedies is the Plaintiff entitled to if any.
Orders
- Special damages of UGX 372,452,331 awarded to the Plaintiff.
- General damages of UGX 20,000,000 awarded to the Plaintiff.
- Exemplary damages of UGX 5,000,000 awarded to the Plaintiff.
- Interest on special damages at 21% per annum from date of filing suit until payment in full.
- Interest on general and exemplary damages at 6% per annum from date of judgment until payment in full.
- Return of the equipment left in South Sudan or the value thereof ordered.
- Costs of the suit awarded to the Plaintiff.
Rules and key headnotes
Legislation cited (7)
Cases cited (8)
- Uganda Telecom Ltd vs. Rodrigo Chacon T/a Andes Alpes Trading
- Donoline v Armco Inc & Others [2002] ILloyd's Rep 425
- National Power PLC v United Gas Co Ltd & Another [1998] All ER (D) 231
- Part Land Hick v Raymond and Reid [1893] AC 22
- Haji Asumani Mutekanga v Equator Growers (U) Ltd (Supreme Court Civil Appeal No. 7 of 1995)
- Robbialac Paints (Uganda) Ltd vs. K.B Construction Ltd [1976] HCB 45
- General and Finance Facilities v Cooks Cars (Ramford) [1963] 1 WLR 644
- Roko Construction Co Ltd v Attorney General (High Court Civil Suit No. 517 of 2005)
Cases citing this judgment (3)
How later Ugandan judgments in the Wakilii corpus have cited this case. Treatment labels come from Sequitur — Uganda’s citator — each backed by a verbatim span from the citing judgment, and are not an assertion that this case is, or is not, good law.
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.