Tom Mukomazi v Jinda International Textile Corporation (Civil Suit No. 106 of 2002)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court held that the plaint disclosed a cause of action despite verification requirements, as verification was the employer's responsibility. The court-appointed quantity surveyor valued completed works at UGX 144,667,452. After payments totalling UGX 98,055,250, a balance of UGX 46,612,202 remained. The court deducted 25% for poor workmanship, awarding the plaintiff UGX 34,000,000. The defendant's counterclaim failed for lack of evidence.
Outcome
Plaintiff awarded UGX 34,000,000 after deduction for poor workmanship; counterclaim dismissed
Facts
In January 2001, the defendant engaged the plaintiff under a building contract to refurbish buildings at the Uganda Spinning Mills factory in Lira. The plaintiff invoiced UGX 147,541,095 and claimed the defendant paid only UGX 60,300,000, leaving UGX 87,241,095 unpaid. The defendant denied liability, alleging the plaintiff failed to carry out works properly, and counterclaimed UGX 91,785,091 for overpayment. The parties agreed to appoint DEC Consultants, building economists, to survey and value the works. The quantity surveyor, Mr. Cyprian Igulot Inyangat, reported that works valued at UGX 144,667,452 had been completed, but noted the workmanship was below standard due to absence of quality specifications in the contract. Documentary evidence showed the defendant paid UGX 98,055,250. The plaintiff's witness maintained the work was of good quality, contradicting the surveyor. The defendant's witnesses, including a district engineer, valued the work at substantially less. The plaintiff also claimed additional works valued at UGX 24,287,445 by the surveyor.
Issues
- Whether the plaint disclosed a cause of action where payment was dependent on verification of works.
- Whether the plaintiff had ensured good workmanship and materials as required under the contract.
- What sum was owed to the plaintiff for work done under the building contract.
- Whether the defendant's counterclaim for overpayment should be allowed.
Orders
- Judgment entered for the plaintiff against the defendant in the sum of UGX 34,000,000.
- Each party to pay 50% of the fees of the surveying consultants.
- No order as to costs.
Rules and key headnotes
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.