Uganda Civil Aviation Authority v Central Plumbing Works Uganda Limited (Miscellaneous Cause 37 of 2023)
Observed later treatment
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court set aside an arbitral award on the ground that the arbitral tribunal was improperly constituted. The parties had by consent amended the contractual arbitration clause to permit CADER to appoint the third arbitrator, contrary to the original agreement which specified the President of the Uganda Institution of Professional Engineers or a High Court judge as the appointing authority. Because the original agreement involved a statutory body and public funds and had been approved by the Solicitor General, the variation required Solicitor General approval under Article 119(5) of the Constitution. The court held that the failure to obtain such approval rendered the appointment of the chairperson irregular and illegal, depriving the tribunal of jurisdiction.
Outcome
Arbitral award set aside; matter may be referred to a properly constituted tribunal
Facts
In 2013, Uganda Civil Aviation Authority (a statutory body) entered into a construction works agreement with Central Plumbing Works (U) Limited for construction of extra water reservoirs at Entebbe International Airport at a contract sum of UGX 835,000,000. The agreement was submitted to and approved by the Solicitor General as required for government contracts. Clause 25.4.1 of the agreement provided that disputes would be arbitrated by three arbitrators, with the third (chairperson) to be appointed by the President of the Uganda Institution of Professional Engineers or, in the event of conflict of interest, by a Justice of the Commercial Division. A dispute arose and the respondent commenced arbitration proceedings in 2020. Each party appointed its arbitrator. Initially the respondent wrote to UIPE for appointment of the third arbitrator. Subsequently, at the applicant's insistence, the matter was registered with CADER. On 29 April 2021 the respondent proposed that the parties execute a consent nominating CADER as the appointing authority for the third arbitrator. The applicant agreed in writing on 5 May 2021, and a consent was executed on 31 May 2021. CADER appointed Ms. Belinda Lutaya Nakiganda as chairperson on 19 August 2021. The tribunal rendered an award in favour of the respondent on 25 November 2022. The applicant then applied to set aside the award, arguing that the variation of the arbitration clause without Solicitor General approval rendered the tribunal's constitution irregular and illegal.
Issues
- Whether the composition of the Arbitral Tribunal in CAD/ARB/14/2021 was improper and irregular in contravention of the clear provisions of the law and the Construction Works Agreement signed between the parties?
- Whether the Arbitral award in CAD/ARB/14/2021 is regular and enforceable?
- What are the remedies available to the parties?
Orders
- The Arbitral Award made by the Arbitral Tribunal in CAD-ARB No. 14 of 2021 is set aside.
- Each party shall meet its costs.
Rules and key headnotes
Legislation cited (4)
- Arbitration and Conciliation Act s.34(2)(a)(v)
- Arbitration and Conciliation Act s.11
- Judicature Act s.14
- Constitution of the Republic of Uganda 1995 as amended Art.119(5)
Cases cited (4)
- Kinyara Sugar Works Ltd v Hajji Kasimbiraine Mohamoud (Miscellaneous Application No. 151 of 2017)
- Agnes Muhindi and Anor v Joash Mugendo [1991] KLR 78; [1988-92] 2 KAR 155
- Haresh Chinnubhai Shah v Rajesh Prabhakar Jhaveri & Anor [2004] (2) R.A.J 179 (Bom)
- Union of India v Builders Corp (P) Ltd AIR 2010 (NOC) 750 (Cal); 2010(5) R.A.J. 548: 2010 (2) Arb.L.R 375
Cases citing this judgment (3)
How later Ugandan judgments in the Wakilii corpus have cited this case. Treatment labels come from Sequitur — Uganda’s citator — each backed by a verbatim span from the citing judgment, and are not an assertion that this case is, or is not, good law.
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.