Umeme Limited v Lwembawo (EDT COMPLAINT 2 of 2012)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The Tribunal found that a meter bypass existed on the complainant's supply line, not a circuit breaker bypass as claimed. However, Umeme failed to provide consumption records demonstrating actual illegal consumption during the disputed period. The Tribunal ruled that the UGX 295,000 charge could not be sustained in the absence of a consumption profile and ordered it credited to the complainant. Power supply was maintained provided the complainant continued to meet his obligations.
Outcome
Complaint partly allowed; penalty charge cancelled and credited to complainant; power supply maintained subject to ongoing payment obligations
Facts
On 1 March 2012, Umeme Limited disconnected Herbert Lwembawo's electricity supply after discovering what it alleged was a meter bypass, meaning energy was being consumed without measurement or payment. Umeme imposed a charge of UGX 295,000 and required payment before reconnection. Lwembawo contended the bypass was of a circuit breaker, not the meter, and was installed by Umeme's contractor to circumvent a faulty circuit breaker during pre-payment meter installation. He claimed the meter was installed on a pole beyond his access. Lwembawo complained to the Electricity Regulatory Authority but received no response. After several months without power, he filed a complaint with the Electricity Disputes Tribunal. The Tribunal ordered interim restoration of supply upon payment of UGX 295,000 as security. Umeme presented technical witnesses and photographic evidence to prove meter bypass. Lwembawo argued his consumption had been consistent and he had no access to the meter.
Issues
- Whether the complainant's electricity supply was lawfully disconnected on grounds of meter bypass.
- Whether the bypass discovered was a meter bypass or a circuit breaker bypass.
- Whether the charge of UGX 295,000 levied by Umeme was justified and properly characterised.
Orders
- The sum of UGX 295,000 levied against Mr. Lwembawo by Umeme be credited to Mr. Lwembawo.
- Mr. Lwembawo's power supply status quo be maintained, provided he continues to meet his obligations to Umeme in respect of energy consumed at the premises.
- Each party to meet its own costs.
Rules and key headnotes
Legislation cited (2)
- Electricity (Primary Grid Code) Regulations 24/2003 clause 7.6.1(c)
- Electricity (Primary Grid Code) Regulations 24/2003 clause 15.5
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.