vambeco Enterprises Ltd v vienna Academy Ltd (HCT-00-CC-CS 419 of 2005)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court held that the plaintiff contractor was entitled to US$22,438.56 representing unpaid certified work done before contract termination. The defendant's termination was unlawful as it failed to comply with the contractual notice provisions in Clause 25(1), which required 14 days' notice to remedy defaults before termination. The court awarded general damages of UGX 18,000,000 for breach of contract representing lost anticipated income from completing the contract.
Outcome
Judgment entered for the plaintiff with damages and costs awarded
Facts
In November 2000, Vienna Academy Ltd contracted Vambeco Enterprises Ltd to construct a multipurpose hall, covered link way, dormitory block and associated works at Kyaliwajala for US$134,982.00. The contract period was four months commencing 1 December 2000. The plaintiff was to receive 25% within two weeks but payment was delayed by two months. Five interim certificates were issued certifying work valued at US$64,306.47 (US$75,238.56 including VAT). The defendant paid only US$52,800.00. Due to delayed payments, the plaintiff slowed down work. On 27 March 2001, the project architect issued a notice citing insufficient materials, labour and activity on site. Two days later, on 29 March 2001, the defendant terminated the contract citing repeated default. The plaintiff contended US$22,405.00 remained unpaid and the termination was unlawful.
Issues
- Whether the plaintiff was entitled to US$22,405.00 for work done under the contract.
- Whether the defendant's termination of the contract constituted a breach of contract.
Orders
- Judgment entered for the plaintiff in the sum of US$22,438.56.
- Interest at court rate on the sum of US$22,438.56 from 7 May 2001 until payment in full.
- General damages awarded to the plaintiff in the sum of UGX 18,000,000.
- The decretal amount to bear interest at court rate from the date of judgment until payment in full.
- The defendant to pay the costs of the suit to the plaintiff.
Rules and key headnotes
Cases cited (1)
- Woodruff v Dupont [1964] EA 404
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.