Webster Construction Equipment Co. Ltd v Nino Engineering Co. Ltd (HCT-00-CC-CS 324 of 2007)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that where a hirer fails to pay the balance of the hire price after the agreed period and the owner continues to provide services despite the breach, the owner must mitigate loss by terminating the contract. The plaintiff was entitled to recover the unpaid balance of the contract price, operator fees, and transport costs, but not damages for the extra period worked beyond the contract period as the plaintiff failed to mitigate its loss.
Outcome
Judgment entered for the plaintiff; defendant liable for special damages of Shs.6,600,000, general damages of Shs.500,000, interest, and costs
Facts
The plaintiff company hired out its motor grader to the defendant company for 15 days at Shs.9,000,000. The defendant paid half the agreed sum at signing; the balance was due after seven days. The grader was delivered on 28 October 2006 and work commenced on 29 October 2006. After seven days, the plaintiff demanded the balance of Shs.4,500,000 but the defendant failed to pay. Work continued until 17 November 2006, five days beyond the contractual period. The defendant also failed to pay the operator fees of Shs.300,000 and the return transport cost of Shs.1,800,000, both of which were the defendant's responsibility under the agreement. The suit was filed on 10 May 2007. Judgment was entered in default of defence after the defendant failed to respond despite proper service.
Issues
- Whether there was a contract between the plaintiff and the defendant for hire of a motor grader.
- Whether the defendant breached the hire agreement by failing to pay the outstanding balance.
- Whether the plaintiff was entitled to damages for the extra period beyond the contractual 15 days.
- What quantum of special and general damages should be awarded to the plaintiff.
Orders
- Special damages of Shs.6,600,000 awarded to the plaintiff.
- General damages of Shs.500,000 awarded to the plaintiff.
- Interest on special damages at court rate from the date of filing the suit till payment in full.
- Interest on general damages at court rate from the date of judgment till payment in full.
- Costs of the suit awarded to the plaintiff.
Rules and key headnotes
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.